How to get a building permit in New York City

The steps to a building permit in New York City: DOB's do-I-need-a-permit check, licensed professionals, DOB NOW filing and the borough pop-up sessions.

Work on a building in New York City, from a new wall to a new boiler, usually begins with the Department of Buildings (DOB). DOB issues permits, runs inspections and enforces the codes, and its permit process has been moved largely online into a system called DOB NOW. The process is not complicated in outline, but the details depend on what the work is, so the first job is to find out whether a permit is needed at all.

Step 1: ask whether you need a permit

DOB's permit page, under "Obtaining a Permit" in the property or business owner section of its site, starts with a tool and a set of pages called "Do I need a permit?" It is the right first stop, because the answer varies with the work and the building. Some work needs a permit; some work does not but still has to follow the code. Do not rely on a contractor's assurance or a neighbor's experience. Check DOB's own page, and if the answer is still unclear, ask DOB or call 311.

Step 2: find the licensed professionals

New York requires many kinds of work to be done by or under licensed professionals, and DOB's site has a page to find them. The permit process draws on their credentials. Check any professional you plan to hire against DOB's lookup for the license, and keep their license information with your records. Department of Buildings describes how DOB is organized.

Step 3: understand the permit by type

DOB's site lists permits by type. The type depends on the work, and each has its own requirements. The "permits by type" pages are the part of DOB's site to use once you know what you are building or changing: they explain what is filed, what is reviewed and what comes after approval.

Two 2026 changes show how the rules move:

  • The 2025 Electrical Code. DOB's site says that in 2026 it requires the 2025 Electrical Code for electrical filings.
  • Local Law 10 of 2026, effective May 3, 2026, changes Site Safety Training requirements.

If your project touches electrical work or involves a site that needs safety training, read those pages before you plan the schedule.

Step 4: file through DOB NOW

DOB NOW is the department's online filing and permit system. Filings, applications and many follow-up steps happen there, and the licensed professional on your project will typically manage the filing. You create or use an account and follow the system's steps for the permit type. DOB's pages explain the process and offer help guides. If you are an owner who wants to understand the filing before hiring, read the permit-type page and the DOB NOW guidance first.

Step 5: check the other agencies

A DOB permit is not the only approval. Depending on the building and the work, other agencies have a say:

  • The Landmarks Preservation Commission. If the building is a landmark or in a historic district, exterior and some other work needs the commission's approval. The commission oversees more than 38,000 landmark properties, 1,470 individual landmarks and 157 historic districts and extensions. Landmarks Preservation Commission describes its role.
  • The Department of City Planning. Zoning decides what may be built on a lot. Planning, zoning and permits covers how permits and zoning fit together.
  • Other agencies. Depending on the work, other city agencies may also have a say. DOB's pages flag the common cases.

The history behind some of these rules is worth knowing. The city's zoning system dates to the 1916 Zoning Resolution, and the Landmarks Preservation Commission was created in 1965 after the loss of Pennsylvania Station. the 1916 zoning resolution and The Landmarks Law and the loss of Penn Station tell those stories.

Step 6: borough pop-up sessions

DOB's borough offices hold small-owner pop-up sessions on the first and third Tuesday of the month, from 4 to 7 p.m. These sessions are meant for owners with small projects who want to ask questions in person. Check DOB's site for the location in your borough and any changes before you go.

Step 7: inspections and sign-off

Permits are not the end. Work is inspected, and the permit's records are updated as the work is completed. Keep the permit and the sign-offs in a folder, because a later buyer, lender or insurer may ask for them, and the same records are on the public side of the city's property information. Buying property in New York City: taxes, records and who to check describes the records a buyer checks.

A way to sequence a small project

Say an owner of a small building wants to replace a boiler. A sensible order:

  1. Read DOB's "Do I need a permit?" page for that kind of work.
  2. Ask the contractor for their license information and check it on DOB's lookup.
  3. Check whether the building is a landmark or in a historic district.
  4. Have the professional file in DOB NOW, using the 2025 Electrical Code for any electrical component.
  5. Attend a pop-up session if there are questions the pages do not answer.
  6. Schedule inspections and keep the sign-off.

Changes on the horizon

New proposals can reshape the process. Among the five charter amendments on the November 3, 2026 ballot was one concerning city-owned property and building permits, and unofficial results reported approval; the Board of Elections certifies final results. Watch DOB's site for any change to filing rules that follows.

Problems and complaints

Unsafe conditions, work without a permit and other building complaints go through 311, which routes them to DOB or another agency. using 311 effectively explains how to report. If you are running a business out of the building, Starting a business and getting a license in New York City covers the licensing side.